The Guma Valley Water Company and its partners have on Friday 27th May 2022 completed the replacements of the leaking Scour and Gate Valves at the Guma Dam Tunnel at Mile 13.
The replacement of the valves that were installed in the mid-1960s is one of the Works packages under the Freetown Water Supply Rehabilitation Project funded by UKAid.
The main objective of the Freetown Water Supply Rehabilitation Project is to improve the reliability of the water supply for the citizens of Freetown, through rehabilitation of the water supply infrastructure and reduction of leakages for improved and reliable access to safe water supply.
Freetown Water, a consortium of IMC Worldwide, BAM Nuttal and Atkins, are responsible for the designs and implementation of the rehabilitation works, which were split into four stages: Feasibility, Preliminary designs, Detailed designs and Construction.
Speaking to this medium, the Planning, Research and Development Manager of Guma Valley Water Company, Ing Ibrahim C. Bah, said the replacement of the Scour and Gate Valves is another major milestone reached by Guma. He added that the replaced valves have been seriously leaking, leading to the loss of millions of litres of water every day.
“It was not safe to do scouring of the dam because of the old age of the scour valve, but with the new valves, the risk of the valves failing or not functioning correctly has been reduced significantly for the next fifty years, at least” Ing Bah asserted.
Over 90% of the water supply to Freetown is supplied from the Guma Dam reservoir and Main Water Treatment Plant at Mile 13. The Guma Dam was built in the 60s and can only reliably provide water supply to the population it was built for at that time—around 800,000. The current population of Freetown approaches 2 million.
The rehabilitation project will increase sustainable access to water supply in Freetown, with the expected impact being a reduction of morbidity and mortality rates associated with incidences of diarrhoea, typhoid and other water-borne diseases.
The project has already completed the following works:
- Fixed the water ingress to the Intake tower;
- Fixed the landing structures at the Intake tower;
- Fixed the leakages at the Treatment Plant and rehabilitated some filters;
- Installed new electrical control panels, mechanical and pneumatic systems at the Main Treatment Plant;
- Installed new high lift pumps at the Spur Road Reservoirs for pumping water to Wilberforce and lower Hill Station;
- Installed bulk flow and District Metering Area meters on the water transmission pipelines;
- Repaired a Gate Valve, and two cross-connection valves at Lakka, etc.
The project in early May 2022 completed the replacement of the 22 Inches transmission pipeline across the Kaningo River at the old Juba bridge.
Meanwhile, work is ongoing to replace 3.2Km of aged transmission pipeline from Mile 13 to Hamilton.